Completed Villas:
1. Villa A1
2. Villa A2
3. Villa H2
Cladding and Tiling Stage:
In this stage, all the stonework, Alucobond, paint work and floor tiles are fabricated and installed.
1. Villa A6 -7
2. Villa A8-9
3. Villa B3
4. Villa B4
5. Villa B7
6. Villa C1
7. Villa C2
8. Villa C14
9. Villa C15
10. Villa D1
11. Villa D10
12. Villa D11
13. Villa D12
14. Villa D13
15. Villa D14-B
16. Villa D18
17. Villa E6
18. Villa E8
19. Villa E9
Plastering Stage:
In this stage, the blockwork is covered with cementing material so that its ready for paint work and cladding.
1. Villa B2
2. Villa B6
3. Villa C8
4. Villa D3
5. Villa D9
6. Villa D14-A
7. Villa E4
8. Villa E5
9. Villa E11
Blockwork Stage:
External and partition walls are constructed.
1. Villa A3
2. Villa A 4-5
3. Villa A 10-11
4. Villa B1
5. Villa B5
6. Villa C3
7. Villa C4
8. Villa C6
9. Villa C7
10. Villa C11
11. Villa C12
12. Villa C13
13. Villa D5
14. Villa D6
15. Villa D7
16. Villa D8
17. Villa E1
18. Villa E2
19. Villa E3
20. Villa E10
21. Villa E12
22. Villa E13
23. Villa E14
24. Villa E15
25. Villa E17
26. Villa F4
27. Villa F7
28. Villa G3
29. Villa G4
30. Villa H3
Concrete Stage:
Columns, reinforced walls and slabs that form the structural frame of the building to support its weight and the imposed loads are constructed. Bitumen coating and isolating materials are used to protect the structural elements from chemical attacks and to prevent water leakage through walls and roofs.
1. Villa C9
2. Villa D17
3. Villa D19
4. Villa E16
5. Villa E18
6. Villa F2
7. Villa F3
8. Villa F5
9. Villa F9
10. Villa G1
11. Villa G2
12. Villa G7
13. Villa H1
14. Villa H4
15. Villa H5
16. Villa H6
Foundations Stage:
The construction phase of the reinforced concrete footings that transfer the loads from columns and walls into the underlying soil.
1. Villa F10
2. Villa F11
Excavations Stage:
It’s the process of cutting and/or filling the ground to reach the soil layer where the foundations can be constructed over on one hand and to adapt with the mass plan levels on the other.