Ohana Hills Progress Report – April 2022

Apr 16, 2022

Completed Villas:

1. Villa A1

2. Villa A2

3. Villa H2

Cladding and Tiling Stage:

In this stage, all the stonework, Alucobond, paint work and floor tiles are fabricated and installed.

1. Villa A6 -7

2. Villa A8-9

3. Villa B3

4. Villa B4

5. Villa B7

6. Villa C1

7. Villa C2

8. Villa C14

9. Villa C15

10. Villa D1

11. Villa D10

12. Villa D11

13. Villa D12

14. Villa D13

15. Villa D14-B

16. Villa D18

17. Villa E6

18. Villa E8

19. Villa E9

Plastering Stage:

In this stage, the blockwork is covered with cementing material so that its ready for paint work and cladding.

1. Villa B2

2. Villa B6

3. Villa C8

4. Villa D3

5. Villa D9

6. Villa D14-A

7. Villa E4

8. Villa E5

9. Villa E11

Blockwork Stage:

External and partition walls are constructed.

1. Villa A3

2. Villa A 4-5

3. Villa A 10-11

4. Villa B1

5. Villa B5

6. Villa C3

7. Villa C4

8. Villa C6

9. Villa C7

10. Villa C11

11. Villa C12

12. Villa C13

13. Villa D5

14. Villa D6

15. Villa D7

16. Villa D8

17. Villa E1

18. Villa E2

19. Villa E3

20. Villa E10

21. Villa E12

22. Villa E13

23. Villa E14

24. Villa E15

25. Villa E17

26. Villa F4

27. Villa F7

28. Villa G3

29. Villa G4

30. Villa H3


Concrete Stage:

Columns, reinforced walls and slabs that form the structural frame of the building to support its weight and the imposed loads are constructed. Bitumen coating and isolating materials are used to protect the structural elements from chemical attacks and to prevent water leakage through walls and roofs.

1. Villa C9

2. Villa D17

3. Villa D19

4. Villa E16

5. Villa E18

6. Villa F2

7. Villa F3

8. Villa F5

9. Villa F9

10. Villa G1

11. Villa G2

12. Villa G7

13. Villa H1

14. Villa H4

15. Villa H5

16. Villa H6


Foundations Stage:

The construction phase of the reinforced concrete footings that transfer the loads from columns and walls into the underlying soil.

1. Villa F10

2. Villa F11


Excavations Stage:

It’s the process of cutting and/or filling the ground to reach the soil layer where the foundations can be constructed over on one hand and to adapt with the mass plan levels on the other.

1. Villa C10

2. Villa F8

Roads:


THANK YOU
WE WILL KEEP YOU UPDATED

Search articles

Book your demo now!

Recent posts