Ohana Hills Progress Report – January 2021

Jan 27, 2021

I. VILLAS CONSTRUCTION PROGRESS

1. Villa A2

Finished Constructing Stages:
a) Attic roof concrete pitched slab
b) Mechanical and electrical pipes and connections
c) Plaster Work
d) Sandtex Paint
e) Cladding
f) Tiling in progress

Luxury Villas In Lebanon - Progress Report Jan2021- img1
Luxury Villas In Lebanon - Progress Report Jan2021- img2
Figure 1: Block Work
Luxury Villas In Lebanon - Progress Report Jan2021- img3
Figure 2: Plaster Work
Luxury Villas In Lebanon - Progress Report Jan2021- img4
Figure 3: Cladding Work
Luxury Villas In Lebanon - Progress Report Jan2021- img5
Figure 4: Block Work
Luxury Villas In Lebanon - Progress Report Jan2021- img6
Figure 5: Cladding Work
Luxury Villas In Lebanon - Progress Report Jan2021- img7
Figure 6: Plaster Work
Luxury Villas In Lebanon - Progress Report Jan2021- img8
Figure 7: Block Work
Luxury Villas In Lebanon - Progress Report Jan2021- img9
Figure 8: Plaster Work
Luxury Villas In Lebanon - Progress Report Jan2021- img10
Figure 9: Cladding Work
Luxury Villas In Lebanon - Progress Report Jan2021- img11
Figure 10: Interior Plaster
Luxury Villas In Lebanon - Progress Report Jan2021- img12
Figure 11: Bedroom Tiling
Luxury Villas In Lebanon - Progress Report Jan2021- img13
Figure 12: Bathroom Tiling
Luxury Villas In Lebanon - Progress Report Jan2021- img14
Figure 13: Alucobond Installation
Luxury Villas In Lebanon - Progress Report Jan2021- img15
Figure 14: MEP Pipes Installation
Luxury Villas In Lebanon - Progress Report Jan2021- img16
Figure 15: Covering the pipes with False Ceiling

2. Villa A3

Finish Construction Stages:
a) Foundations
b) Slab on Grade
c) Basement Columns and Retaining Walls
d) Swimming Pool

Luxury Villas In Lebanon - Progress Report Jan2021- img17
Luxury Villas In Lebanon - Progress Report Jan2021- img18
Figure 1: Foundations and Slab on Grade
Luxury Villas In Lebanon - Progress Report Jan2021- img19
Figure 2: Basement Columns and Retaining Walls
Luxury Villas In Lebanon - Progress Report Jan2021- img20
Figure 3: RC Swimming Pool

2. Villa B1

Finished construction stages:
a) Basement block/partition walls
b) Outer walls insulation
c) RC Swimming Pool

Luxury Villas In Lebanon - Progress Report Jan2021- img21
Luxury Villas In Lebanon - Progress Report Jan2021- img22
Figure 1: RC Swimming Pool
Luxury Villas In Lebanon - Progress Report Jan2021- img23
Figure 2: Outer walls insulation layers

3. Villa B2

Finished construction stages:
a) Slab on grade
b) Basement columns
c) Ground floor post-tension slab
d) Block/partition walls at basement level

Luxury Villas In Lebanon - Progress Report Jan2021- img24
Luxury Villas In Lebanon - Progress Report Jan2021- img25
Figure 1: Slab on grade
Luxury Villas In Lebanon - Progress Report Jan2021- img26
Figure 2: Basement retaining walls and PT slab
reinforcement
Luxury Villas In Lebanon - Progress Report Jan2021- img27
Figure 3: PT slab after concrete casting and block walls
work

4. Villa B3

Finished construction stages:
a) Foundations
b) Basement slab on grade
c) Basement Columns and retaining walls
d) Swimming Pool
e) Ground floor reinforced concrete slab
f) Block/partition walls

Luxury Villas In Lebanon - Progress Report Jan2021- img28
Luxury Villas In Lebanon - Progress Report Jan2021- img29
Figure 1: Ground Floor Slab

5. Villa B4

Finished construction stages:
a) First floor PT slab
b) Swimming pool

Luxury Villas In Lebanon - Progress Report Jan2021- img30
Luxury Villas In Lebanon - Progress Report Jan2021- img31
Figure 1: First floor slab formwork
Luxury Villas In Lebanon - Progress Report Jan2021- img32
Figure 2: PT slab strands and RC details
Luxury Villas In Lebanon - Progress Report Jan2021- img33
Figure 3: PT concrete slab view 1
Luxury Villas In Lebanon - Progress Report Jan2021- img34
Figure 4: PT concrete slab view 2 RC swimming
Luxury Villas In Lebanon - Progress Report Jan2021- img35
Figure 5: RC swimming pool

6. Villa B5

Finished construction stages
a) Slab on grade
b) Ground floor columns
c) First Floor PT slab
d) Block/partition walls

Luxury Villas In Lebanon - Progress Report Jan2021- img36
Luxury Villas In Lebanon - Progress Report Jan2021- img37
Figure 1: Slab on grade reinforcements
Luxury Villas In Lebanon - Progress Report Jan2021- img38
Figure 2: Slab on grade after concrete cast
Luxury Villas In Lebanon - Progress Report Jan2021- img39
Figure 3: Concrete casting of first floor PT slab
Luxury Villas In Lebanon - Progress Report Jan2021- img40
Figure 4: First floor PT slab

7. Villa B6

Finished construction stages:
a) Ground floor PT slab

Luxury Villas In Lebanon - Progress Report Jan2021- img41
Luxury Villas In Lebanon - Progress Report Jan2021- img42
Figure 1: Form Work
Luxury Villas In Lebanon - Progress Report Jan2021- img43
Figure 2: After Concrete Casting

8. Villa B7

Finished construction stages:
a) Ground floor PT slab
b) RC Swimming Pool

Luxury Villas In Lebanon - Progress Report Jan2021- img44
Luxury Villas In Lebanon - Progress Report Jan2021- img45
Figure 1: PT slab During Concrete Casting
Luxury Villas In Lebanon - Progress Report Jan2021- img46
Figure 2: PT slab after Concrete Casting
Luxury Villas In Lebanon - Progress Report Jan2021- img47
Figure 3: Basement Block Work
Luxury Villas In Lebanon - Progress Report Jan2021- img48
Figure 4: RC Swimming Pool

9. Villa C1

Finished construction stages:
a) Block/partition walls.
b) RC Swimming Pool

Luxury Villas In Lebanon - Progress Report Jan2021- img49
Luxury Villas In Lebanon - Progress Report Jan2021- img50
Figure 1: Swimming pool raft
Luxury Villas In Lebanon - Progress Report Jan2021- img51
Figure 2: RC Swimming Pool

10. Villa C2

Finished construction stages:
a) Basement block/partition walls

Luxury Villas In Lebanon - Progress Report Jan2021- img52
Luxury Villas In Lebanon - Progress Report Jan2021- img53
Figure 1: Basement Block/Partition Walls

11. Villa C3

Finished construction stages:
a) 1st Floor PT slab
b) Ground floor block/partition walls

Luxury Villas In Lebanon - Progress Report Jan2021- img54
Luxury Villas In Lebanon - Progress Report Jan2021- img55
Figure 1: C1 3st floor PT slab
Luxury Villas In Lebanon - Progress Report Jan2021- img56
Figure 2: C3 block/partition walls

12. Villa C4

Finished construction stages:
a) 1st Floor PT slab

Luxury Villas In Lebanon - Progress Report Jan2021- img57
Luxury Villas In Lebanon - Progress Report Jan2021- img58
Figure 1: 1st floor PT slab formwork
Luxury Villas In Lebanon - Progress Report Jan2021- img59
Figure 2: 1st floor PT slab

13. Villa C6

Finished construction stages:
a) Basement block/partition walls

Luxury Villas In Lebanon - Progress Report Jan2021- img60
Luxury Villas In Lebanon - Progress Report Jan2021- img61
Figure 1: Block walls and exterior isolation

14. Villa C7

Finished construction stages:
a) Foundations at the basement level
b) Swimming Pool

Luxury Villas In Lebanon - Progress Report Jan2021- img62
Luxury Villas In Lebanon - Progress Report Jan2021- img63
Figure 1: Basement block/partition wall
Luxury Villas In Lebanon - Progress Report Jan2021- img64
Figure 2: RC Swimming Pool

15. Villa C8

Finished construction stages:
a) Foundations
b) Slab on grade
c) Basement columns
d) Ground Floor PT slab

Luxury Villas In Lebanon - Progress Report Jan2021- img65
Luxury Villas In Lebanon - Progress Report Jan2021- img66
Figure 1: Foundations and slab on grade reinforcements
Luxury Villas In Lebanon - Progress Report Jan2021- img67
Figure 2: Concrete Casting of Foundations and Slab on Grade
Luxury Villas In Lebanon - Progress Report Jan2021- img68
Figure 3: Concrete Casting of Basement Columns
Luxury Villas In Lebanon - Progress Report Jan2021- img69
Figure 4: 1st floor PT slab

16. Villa C11

Finished construction stages:
a) Foundations

Luxury Villas In Lebanon - Progress Report Jan2021- img70
Luxury Villas In Lebanon - Progress Report Jan2021- img71
Figure 1: Casting of Foundations

17. Villa C14

Finished construction stages:
a) Ground Floor Slab Formwork
b) Ground Floor PT slab
c) Block/partition walls

Luxury Villas In Lebanon - Progress Report Jan2021- img72
Luxury Villas In Lebanon - Progress Report Jan2021- img73
Figure 1: Ground Floor Slab Formwork
Luxury Villas In Lebanon - Progress Report Jan2021- img74
Figure 2: Ground Floor PT slab and block walls
Luxury Villas In Lebanon - Progress Report Jan2021- img75
Figure 3: Walls External Isolations
Luxury Villas In Lebanon - Progress Report Jan2021- img76
Figure 4: Ground Floor PT Slab Top View

18. Villa C15

Finished construction stages:
a) Ground Floor PT slab
b) Block/partition walls

Luxury Villas In Lebanon - Progress Report Jan2021- img77
Luxury Villas In Lebanon - Progress Report Jan2021- img78
Figure 1: Ground Floor Slab Form Work Ground Floor PT slab
Luxury Villas In Lebanon - Progress Report Jan2021- img79
Figure 2: Ground Floor PT slab

20. Villa D1

Finished construction stages:
a) Excavation and Foundations
b) Column Necks
c) Soil Fill and Slab on Grade
d) Basement Columns and Retaining Walls
e) Ground Floor PT Slab

Luxury Villas In Lebanon - Progress Report Jan2021- img80
Luxury Villas In Lebanon - Progress Report Jan2021- img81
Figure 1: Foundations and Column Necks
Luxury Villas In Lebanon - Progress Report Jan2021- img82
Figure 2: Soil Fill and MEP works
Luxury Villas In Lebanon - Progress Report Jan2021- img83
Figure 3: Slab on Grade Reinforcements
Luxury Villas In Lebanon - Progress Report Jan2021- img84
Figure 4: Basement Columns
Luxury Villas In Lebanon - Progress Report Jan2021- img85
Figure 5: Basement Columns Ground Floor PT Slab

21. Villa D3

Finished construction stages:
a) Excavation and Foundations
b) Column Necks
c) Soil Fill and Slab on Grade
d) Basement Columns and Retaining Walls
e) Ground Floor PT Slab Formwork

Luxury Villas In Lebanon - Progress Report Jan2021- img86
Luxury Villas In Lebanon - Progress Report Jan2021- img87
Figure 1: The casting of the Blinding Concrete Layer
Luxury Villas In Lebanon - Progress Report Jan2021- img88
Figure 2: Foundations
Luxury Villas In Lebanon - Progress Report Jan2021- img89
Figure 3: Slab on Grade and Column Necks
Luxury Villas In Lebanon - Progress Report Jan2021- img90
Figure 4: Ground Floor Slab Formwork

22. Villa D5

Finished construction stages:
a) Excavation and Foundations
b) Column Necks
c) Tie Beams

Luxury Villas In Lebanon - Progress Report Jan2021- img91
Luxury Villas In Lebanon - Progress Report Jan2021- img92
Figure 1: Intermediate Tie Beams and Column Necks

23. Villa D6

Finished construction stages:
a) Excavation and Foundations
b) Column Necks
c) Soil Fill and Slab on Grade
d) Basement Columns and Retaining Walls

Luxury Villas In Lebanon - Progress Report Jan2021- img92
Luxury Villas In Lebanon - Progress Report Jan2021- img93
Figure 2: Foundations Reinforcements
Luxury Villas In Lebanon - Progress Report Jan2021- img94
Figure 3: Basement Slab on Grade and Columns

24. Villa D7

Finished construction stages:
a) Excavation and Foundations
b) Column Necks
c) Soil Fill and Slab on Grade
d) Basement Columns and Retaining Walls

Luxury Villas In Lebanon - Progress Report Jan2021- img95
Luxury Villas In Lebanon - Progress Report Jan2021- img96
Figure 1: Foundations Reinforcements
Luxury Villas In Lebanon - Progress Report Jan2021- img97
Figure 2: Foundations and Column Necks
Luxury Villas In Lebanon - Progress Report Jan2021- img98
Figure 3: Slab on Grade preparations

25. Villa D8

Finished construction stages:
a) Excavation and Foundations
b) Column Necks
c) Soil Fill and Slab on Grade
d) Basement Columns

Luxury Villas In Lebanon - Progress Report Jan2021- img99
Luxury Villas In Lebanon - Progress Report Jan2021- img100
Figure 1: Basement Slab on Grade and Columns

26. Villa D9

Finished construction stage:
a) Excavation and Foundations

Luxury Villas In Lebanon - Progress Report Jan2021- img101
Luxury Villas In Lebanon - Progress Report Jan2021- img102
Figure 1: Foundations and Bitumen Isolation

27. Villa D10

Finished construction stages:
a) Ground Floor Slab
b) Block/partition walls
c) Swimming Pool

Luxury Villas In Lebanon - Progress Report Jan2021- img103
Luxury Villas In Lebanon - Progress Report Jan2021- img104
Figure 1: Parking Entrance
Luxury Villas In Lebanon - Progress Report Jan2021- img105
Figure 2: Interior Partition Walls
Luxury Villas In Lebanon - Progress Report Jan2021- img106
Figure 3: RC Swimming Pool

28. Villa D11

Finished construction stages:
a) Foundations
b) Slab on Grade
c) Basement Columns
d) Ground Floor PT slab

Luxury Villas In Lebanon - Progress Report Jan2021- img107
Luxury Villas In Lebanon - Progress Report Jan2021- img107
Figure 1: Foundations and Slab on Grade Reinforcements
Luxury Villas In Lebanon - Progress Report Jan2021- img108
Figure 2: Basement Columns and Slab on Grade
Luxury Villas In Lebanon - Progress Report Jan2021- img109
Figure 3: PT Ground Floor Slab After Concrete Casting

29. Villa D14 A

Finished construction stages:
a) Foundations
b) Slab on Grade
c) Basement Columns
d) 1st Floor PT slab

Luxury Villas In Lebanon - Progress Report Jan2021- img110
Luxury Villas In Lebanon - Progress Report Jan2021- img111
Figure 1: Ground Floor Columns and 1st Floor PT Slab

30. Villa D14 B

Finished construction stages:
a) Foundations
b) Slab on Grade
c) Basement Columns
d) 1st Floor PT slab

Luxury Villas In Lebanon - Progress Report Jan2021- img112
Luxury Villas In Lebanon - Progress Report Jan2021- img113
Figure 1: Ground Floor Columns and 1st Floor PT Slab

31. Villa D18

Finished construction stages:
a) Parking Extension
b) Slab on Grade
c) Ground Floor Columns

Luxury Villas In Lebanon - Progress Report Jan2021- img114
Luxury Villas In Lebanon - Progress Report Jan2021- img115
Figure 1: Slab on Grade and Ground Floor Columns
Luxury Villas In Lebanon - Progress Report Jan2021- img116
Figure 2: Parking Extension

32. Villa E1

Finished construction stages:
a) Slab on Grade
b) Basement Columns
c) Ground Floor PT Slab

Luxury Villas In Lebanon - Progress Report Jan2021- img117
Luxury Villas In Lebanon - Progress Report Jan2021- img118
Figure 1: Slab on Grade Concrete Casting
Luxury Villas In Lebanon - Progress Report Jan2021- img119
Figure 2: Basement Columns and Ground Floor PT slab

33. Villa E2

Finished construction stages:
a) Slab on Grade
b) Basement Columns
c) Ground Floor PT Slab

Luxury Villas In Lebanon - Progress Report Jan2021- img120
Luxury Villas In Lebanon - Progress Report Jan2021- img121
Figure 1: Slab on Grade and Basement
Luxury Villas In Lebanon - Progress Report Jan2021- img122
Figure 2: Ground Floor PT Slab Formwork
Luxury Villas In Lebanon - Progress Report Jan2021- img123
Figure 3: Ground Floor PT Slab After Concrete Castin

34. Villa E13

Finished construction stages:
a) Foundations and Slab on Grade
b) Basement Columns and Retaining Walls

Luxury Villas In Lebanon - Progress Report Jan2021- img124
Luxury Villas In Lebanon - Progress Report Jan2021- img125
Figure 1: Foundations and Slab on Grade
Luxury Villas In Lebanon - Progress Report Jan2021- img126
Figure 2: Basement Columns and Retaining Walls

35. Villa F7

Finished construction stages:
a) Excavation

Luxury Villas In Lebanon - Progress Report Jan2021- img127
Luxury Villas In Lebanon - Progress Report Jan2021- img128
Figure 1: Excavations

II. WALLS

Zone B

Luxury Villas In Lebanon - Progress Report Jan2021- img129
Luxury Villas In Lebanon - Progress Report Jan2021- img130
Luxury Villas In Lebanon - Progress Report Jan2021- img131
Luxury Villas In Lebanon - Progress Report Jan2021- img132

Zone D

Luxury Villas In Lebanon - Progress Report Jan2021- img133
Luxury Villas In Lebanon - Progress Report Jan2021- img134

III. Roads and Infrastructures

  • All main roads are paved
Luxury Villas In Lebanon - Progress Report Jan2021- img135
Luxury Villas In Lebanon - Progress Report Jan2021- img136
  • All main roads subgrade layers are finished and ready for asphalt pavement.
Luxury Villas In Lebanon - Progress Report Jan2021- img137
Luxury Villas In Lebanon - Progress Report Jan2021- img138
Luxury Villas In Lebanon - Progress Report Jan2021- img139
Luxury Villas In Lebanon - Progress Report Jan2021- img140
Luxury Villas In Lebanon - Progress Report Jan2021- img141

THANK YOU
WE WILL KEEP YOU UPDATED