Ohana Hills Progress Report – April 2021

Apr 23, 2021

I. VILLAS CONSTRUCTION PROGRESS

1. Villa C11

Finished villas construction stages in the last 4 months
a) Excavation
b) Foundations
c) Slab on grade
d) Basement Columns and retaining walls
e) Ground Floor PT slab
f) Partition and exterior walls
g) Bitumen Isolation

ohana hills - progress report - April 2021 - img2

2. Villa C12

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground Floor columns
e) First Floor PT slab

ohana hills - progress report - April 2021 - img3
ohana hills - progress report - April 2021 - img4

3. Villa C13

Finished construction stages:
a) Excavation

ohana hills - progress report - April 2021 - img5

4. Villa D1

Finished construction stages:
a) Swimming pool

ohana hills - progress report - April 2021 - img6
ohana hills - progress report - April 2021 - img7

5. Villa D3

Finished construction stages:
a) Swimming pool

ohana hills - progress report - April 2021 - img8
ohana hills - progress report - April 2021 - img9

6. Villa D5

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground Floor columns
e) First Floor PT slab

ohana hills - progress report - April 2021 - img10
ohana hills - progress report - April 2021 - img11
ohana hills - progress report - April 2021 - img12

7. Villa D6

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Basement Columns and retaining walls
e) Ground Floor PT slab
f) Partition and exterior walls
g) Bitumen Isolation

ohana hills - progress report - April 2021 - img13

8. Villa D7

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Basement Columns and retaining walls
e) Ground Floor PT slab
f) Partition and exterior walls

ohana hills - progress report - April 2021 - img14
ohana hills - progress report - April 2021 - img15

9. Villa D8

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Basement Columns and retaining walls
e) Ground Floor PT slab
f) Partition and exterior walls
g) Swimming pool

ohana hills - progress report - April 2021 - img16
ohana hills - progress report - April 2021 - img17
ohana hills - progress report - April 2021 - img18

10. Villa D9

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Basement Columns and retaining walls
e) Ground Floor PT slab
f) Partition and exterior walls
g) Swimming pool

ohana hills - progress report - April 2021 - img19
ohana hills - progress report - April 2021 - img20
ohana hills - progress report - April 2021 - img21
ohana hills - progress report - April 2021 - img22

11. Villa D12

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground Floor PT slab
e) Partition and exterior walls
g) Swimming pool

ohana hills - progress report - April 2021 - img23
ohana hills - progress report - April 2021 - img24

12. Villa D13

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground Floor PT slab
e) Basement Columns and retaining walls

ohana hills - progress report - April 2021 - img25
ohana hills - progress report - April 2021 - img26
ohana hills - progress report - April 2021 - img27

13. Villa D14-A

Finished construction stages:
a) Partition and exterior walls

ohana hills - progress report - April 2021 - img28

14. Villa D14-B

Finished construction stages:
a) Partition and exterior walls

ohana hills - progress report - April 2021 - img29

15. Villa D18

Finished construction stages:
a) Partition and exterior walls
b) First Floor PT slab

ohana hills - progress report - April 2021 - img30
ohana hills - progress report - April 2021 - img31
ohana hills - progress report - April 2021 - img32

16. Villa E3

Finished construction stages:
a) Excavation
b) Foundations
c) Columns and retaining walls necks

ohana hills - progress report - April 2021 - img33
ohana hills - progress report - April 2021 - img34
ohana hills - progress report - April 2021 - img35

17. Villa E4

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground floor Columns
e) First floor PT slab

ohana hills - progress report - April 2021 - img36
ohana hills - progress report - April 2021 - img37
ohana hills - progress report - April 2021 - img38
ohana hills - progress report - April 2021 - img39

18. Villa E5

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground floor Columns

ohana hills - progress report - April 2021 - img40
ohana hills - progress report - April 2021 - img41

19. Villa E6

Finished construction stages:
a) Excavation
b) Foundations
c) Basement slab on grade
d) Basement columns and retaining walls

ohana hills - progress report - April 2021 - img43
ohana hills - progress report - April 2021 - img44
ohana hills - progress report - April 2021 - img45

20. Villa E8

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Column necks

ohana hills - progress report - April 2021 - img49
ohana hills - progress report - April 2021 - img50

21. Villa E9

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground floor Columns
e) First floor PT slab

ohana hills - progress report - April 2021 - img51

22. Villa E10

Finished construction stages:
a) Excavation
b) Foundations

ohana hills - progress report - April 2021 - img52
ohana hills - progress report - April 2021 - img53

23. Villa E11

Finished construction stages:
a) Excavation

ohana hills - progress report - April 2021 - img54

24. Villa E12

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground floor Columns

ohana hills - progress report - April 2021 - img55

25. Villa E14

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground floor Columns

ohana hills - progress report - April 2021 - img56
ohana hills - progress report - April 2021 - img57

26. Villa E15

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground floor Columns

ohana hills - progress report - April 2021 - img58

27. Villa F7

Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade

ohana hills - progress report - April 2021 - img59
ohana hills - progress report - April 2021 - img60
ohana hills - progress report - April 2021 - img61
ohana hills - progress report - April 2021 - img62

II. Phase 2

1. Villa A4-A5

Finished construction stages:
a) Excavation
b) Foundations
c) Column Necks

ohana hills - progress report - April 2021 - img63
DCIM\100GOPRO\GOPR0514.JPG
ohana hills - progress report - April 2021 - img64
ohana hills - progress report - April 2021 - img65

2. Villa A6-A7

Finished construction stages:
a) Excavation
b) Foundations
c) Column Necks

ohana hills - progress report - April 2021 - img66
ohana hills - progress report - April 2021 - img67

3. Villa A8-A9

Finished construction stages:
a) Excavation
b) Foundations
c) Column Necks

ohana hills - progress report - April 2021 - img67
ohana hills - progress report - April 2021 - img68

4. Villa A10-A11

Finished construction stages:
a) Excavation
b) Foundations
c) Column Necks

ohana hills - progress report - April 2021 - img69

THANK YOU