I. VILLAS CONSTRUCTION PROGRESS
1. Villa C11
Finished villas construction stages in the last 4 months
a) Excavation
b) Foundations
c) Slab on grade
d) Basement Columns and retaining walls
e) Ground Floor PT slab
f) Partition and exterior walls
g) Bitumen Isolation
![ohana hills - progress report - April 2021 - img2](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6616-1024x683.jpg)
2. Villa C12
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground Floor columns
e) First Floor PT slab
![ohana hills - progress report - April 2021 - img3](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6617-1024x683.jpg)
![ohana hills - progress report - April 2021 - img4](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6549-1024x683.jpg)
3. Villa C13
Finished construction stages:
a) Excavation
![ohana hills - progress report - April 2021 - img5](https://ohana-hills.com/wp-content/uploads/2021/04/Excavation-1024x683.jpg)
4. Villa D1
Finished construction stages:
a) Swimming pool
![ohana hills - progress report - April 2021 - img6](https://ohana-hills.com/wp-content/uploads/2021/01/image-84.png)
![ohana hills - progress report - April 2021 - img7](https://ohana-hills.com/wp-content/uploads/2021/04/pool-1024x683.jpg)
5. Villa D3
Finished construction stages:
a) Swimming pool
![ohana hills - progress report - April 2021 - img8](https://ohana-hills.com/wp-content/uploads/2021/01/image-90.png)
![ohana hills - progress report - April 2021 - img9](https://ohana-hills.com/wp-content/uploads/2021/04/pool-1-1024x683.jpg)
6. Villa D5
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground Floor columns
e) First Floor PT slab
![ohana hills - progress report - April 2021 - img10](https://ohana-hills.com/wp-content/uploads/2021/01/image-95.png)
![ohana hills - progress report - April 2021 - img11](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6548-1024x683.jpg)
![ohana hills - progress report - April 2021 - img12](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6550-1024x683.jpg)
7. Villa D6
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Basement Columns and retaining walls
e) Ground Floor PT slab
f) Partition and exterior walls
g) Bitumen Isolation
![ohana hills - progress report - April 2021 - img13](https://ohana-hills.com/wp-content/uploads/2021/01/image-97.png)
8. Villa D7
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Basement Columns and retaining walls
e) Ground Floor PT slab
f) Partition and exterior walls
![ohana hills - progress report - April 2021 - img14](https://ohana-hills.com/wp-content/uploads/2021/01/image-100.png)
![ohana hills - progress report - April 2021 - img15](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6553-1024x683.jpg)
9. Villa D8
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Basement Columns and retaining walls
e) Ground Floor PT slab
f) Partition and exterior walls
g) Swimming pool
![ohana hills - progress report - April 2021 - img16](https://ohana-hills.com/wp-content/uploads/2021/01/image-104.png)
![ohana hills - progress report - April 2021 - img17](https://ohana-hills.com/wp-content/uploads/2021/04/pool-2-1024x683.jpg)
![ohana hills - progress report - April 2021 - img18](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6554-1024x683.jpg)
10. Villa D9
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Basement Columns and retaining walls
e) Ground Floor PT slab
f) Partition and exterior walls
g) Swimming pool
![ohana hills - progress report - April 2021 - img19](https://ohana-hills.com/wp-content/uploads/2021/01/image-106.png)
![ohana hills - progress report - April 2021 - img20](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6626-1024x683.jpg)
![ohana hills - progress report - April 2021 - img21](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6557-1024x683.jpg)
![ohana hills - progress report - April 2021 - img22](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6556-1024x683.jpg)
11. Villa D12
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground Floor PT slab
e) Partition and exterior walls
g) Swimming pool
![ohana hills - progress report - April 2021 - img23](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6624-1024x683.jpg)
![ohana hills - progress report - April 2021 - img24](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6599-1024x683.jpg)
12. Villa D13
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground Floor PT slab
e) Basement Columns and retaining walls
![ohana hills - progress report - April 2021 - img25](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6014-1024x683.jpg)
![ohana hills - progress report - April 2021 - img26](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6015-1024x683.jpg)
![ohana hills - progress report - April 2021 - img27](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6552-1024x683.jpg)
13. Villa D14-A
Finished construction stages:
a) Partition and exterior walls
![ohana hills - progress report - April 2021 - img28](https://ohana-hills.com/wp-content/uploads/2021/01/image-116.png)
14. Villa D14-B
Finished construction stages:
a) Partition and exterior walls
![ohana hills - progress report - April 2021 - img29](https://ohana-hills.com/wp-content/uploads/2021/01/image-119.png)
15. Villa D18
Finished construction stages:
a) Partition and exterior walls
b) First Floor PT slab
![ohana hills - progress report - April 2021 - img30](https://ohana-hills.com/wp-content/uploads/2021/01/image-120.png)
![ohana hills - progress report - April 2021 - img31](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6542-1024x683.jpg)
![ohana hills - progress report - April 2021 - img32](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6573-1024x683.jpg)
16. Villa E3
Finished construction stages:
a) Excavation
b) Foundations
c) Columns and retaining walls necks
![ohana hills - progress report - April 2021 - img33](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6020-1024x683.jpg)
![ohana hills - progress report - April 2021 - img34](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6571-1024x683.jpg)
![ohana hills - progress report - April 2021 - img35](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6572-1024x683.jpg)
17. Villa E4
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground floor Columns
e) First floor PT slab
![ohana hills - progress report - April 2021 - img36](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6516-1024x683.jpg)
![ohana hills - progress report - April 2021 - img37](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6543-1024x683.jpg)
![ohana hills - progress report - April 2021 - img38](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6019-1024x683.jpg)
![ohana hills - progress report - April 2021 - img39](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6591-1024x683.jpg)
18. Villa E5
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground floor Columns
![ohana hills - progress report - April 2021 - img40](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6575-1024x683.jpg)
![ohana hills - progress report - April 2021 - img41](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6544-1024x683.jpg)
19. Villa E6
Finished construction stages:
a) Excavation
b) Foundations
c) Basement slab on grade
d) Basement columns and retaining walls
![ohana hills - progress report - April 2021 - img43](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6018-1024x683.jpg)
![ohana hills - progress report - April 2021 - img44](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6593-1024x683.jpg)
![ohana hills - progress report - April 2021 - img45](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6546-1024x683.jpg)
20. Villa E8
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Column necks
![ohana hills - progress report - April 2021 - img49](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6595-1024x683.jpg)
![ohana hills - progress report - April 2021 - img50](https://ohana-hills.com/wp-content/uploads/2021/04/1-Blinding-Layer-Preparation-1024x683.jpg)
21. Villa E9
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground floor Columns
e) First floor PT slab
![ohana hills - progress report - April 2021 - img51](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6597-1024x683.jpg)
22. Villa E10
Finished construction stages:
a) Excavation
b) Foundations
![ohana hills - progress report - April 2021 - img52](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6564-1024x683.jpg)
![ohana hills - progress report - April 2021 - img53](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6598-1024x683.jpg)
23. Villa E11
Finished construction stages:
a) Excavation
![ohana hills - progress report - April 2021 - img54](https://ohana-hills.com/wp-content/uploads/2021/04/Excavation-1-1024x683.jpg)
24. Villa E12
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground floor Columns
![ohana hills - progress report - April 2021 - img55](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6602-1024x683.jpg)
25. Villa E14
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground floor Columns
![ohana hills - progress report - April 2021 - img56](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6604-1024x683.jpg)
![ohana hills - progress report - April 2021 - img57](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6569-1024x683.jpg)
26. Villa E15
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
d) Ground floor Columns
![ohana hills - progress report - April 2021 - img58](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6606-1024x683.jpg)
27. Villa F7
Finished construction stages:
a) Excavation
b) Foundations
c) Slab on grade
![ohana hills - progress report - April 2021 - img59](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6569-1024x683.jpg)
![ohana hills - progress report - April 2021 - img60](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6567-1024x683.jpg)
![ohana hills - progress report - April 2021 - img61](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6603-1024x683.jpg)
![ohana hills - progress report - April 2021 - img62](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6568-1024x683.jpg)
II. Phase 2
1. Villa A4-A5
Finished construction stages:
a) Excavation
b) Foundations
c) Column Necks
![ohana hills - progress report - April 2021 - img63](https://ohana-hills.com/wp-content/uploads/2021/04/GOPR0514-1024x768.jpg)
![ohana hills - progress report - April 2021 - img64](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6476-1024x683.jpg)
![ohana hills - progress report - April 2021 - img65](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6475-1024x683.jpg)
2. Villa A6-A7
Finished construction stages:
a) Excavation
b) Foundations
c) Column Necks
![ohana hills - progress report - April 2021 - img66](https://ohana-hills.com/wp-content/uploads/2021/04/GOPR0513-1024x768.jpg)
![ohana hills - progress report - April 2021 - img67](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6677-1024x683.jpg)
3. Villa A8-A9
Finished construction stages:
a) Excavation
b) Foundations
c) Column Necks
![ohana hills - progress report - April 2021 - img67](https://ohana-hills.com/wp-content/uploads/2021/04/DSC_6680-1024x683.jpg)
![ohana hills - progress report - April 2021 - img68](https://ohana-hills.com/wp-content/uploads/2021/04/GOPR0510-1024x768.jpg)
4. Villa A10-A11
Finished construction stages:
a) Excavation
b) Foundations
c) Column Necks
![ohana hills - progress report - April 2021 - img69](https://ohana-hills.com/wp-content/uploads/2021/04/GOPR0509-1024x768.jpg)