I. VILLAS CONSTRUCTION PROGRESS
1. Villa A2
Construction stage:
a) Columns at the basement level are constructed
b) Mid retaining walls are executed
c) Columns and walls in contact with soil are isolated using Bitumen
d) MEP pipes are installed along with the columns
e) Slab on grade is executed
f) Swimming pool is under construction
2. Villa B1
Construction stages:
a) Soil fill is compacted
b) Tie beams are constructed
c) Slab on grade reinforcements are isolated from the underlying soil using a nylon sheet
d) Manholes and MEP system at the slab on grade level is executed
e) Slab on grade has been cast
3. Villa B4
Construction stages:
a) Swimming Pool is being excavated
b) Foundations are ready for construction
4. Villa B5
Construction stages:
a) Villa B5 is currently being excavated
5. Villa B6
Construction stages:
a) Foundations formwork and reinforcements are constructed
b) Concrete foundations are cast
c) MEP works at the basement level is prepared
d) Tie beams and slab on grade are constructed over a nylon isolation sheet in the lower level of the basement floor
e) Spandrel beams are constructed to carry the upper level of the basement floor
6. Villa B7
Construction stages:
a) Columns necks are constructed up to the slab on grade level
b) Concrete in contact with soil is isolated with Bitumen
c) Soil fill is added
d) Tie beams are constructed
e) MEP works at the basement level is prepared
f) Slab on grade reinforcements are distributed over a nylon sheet
g) Slab on grade concrete has been cast
7. Villa C1
Construction stages:
a) Foundations formwork and reinforcements are constructed
b) Concrete foundations, column necks, and retaining walls are cast and isolated with bitumen
c) Soil fill is added to reach the basement level
d) Tie beams and slab on grade are being executed
8. Villa C2
Construction stages:
a) NBlinding layer has been cast
b) Foundations formwork and reinforcements are constructed
c) Concrete foundations, column necks, and retaining walls are cast and isolated with bitumen
d) Soil fill is added to reach the basement level
9. Villa C3
Construction stages:
a) Soil is excavated to reach the rock layer
b) Blinding layer has been cast
c) Foundations have been constructed
10. Villa C4
Construction stages:
Villa C4 is currently in the excavation stage.
11. Villa C6
Construction stages:
a) Excavations are finished
b) Blinding layer has been cast
c)n Foundations formwork and reinforcements are constructed
d) Concrete foundations have been cast
12. Villa C7
Construction stages:
a) Excavations are done
b) Blinding layer has been cast
c) Foundations formwork and reinforcements are constructed
d) Swimming pool is excavated
13. Villa C8
Construction stages:
a) Villa C8 is currently in the excavation stage
14. Villa D10
Construction stages:
a) Villa D10 is currently in the excavation stage
II. WALLS CONSTRUCTION PROGRESS
1. Walls in Zone A
- Walls in Zone B
- Walls in Zone E
III.ROADS CONSTRUCTION PROGRESS
1. Northern Road
The remaining part of northern is ready for the asphalt pavement, manholes and drainage pipes are being installed.
2. North-western Exit
The north-western exit is currently being excavated and drainage pipes are being installed.
3. Western Road
The western road is excavated, base-coarse laid and pipes installed.
4. Southern Road
Some parts of the southern road are ready for asphalt pavement and the rest is under excavations. Infrastructure pipes are being installed.
5. Southern Exit
The southern exit is currently under excavation.
THANK YOU
WE WILL KEEP YOU UPDATED