Ohana Hills Progress Report – August 2020

Sep 28, 2020

I. VILLAS CONSTRUCTION PROGRESS

1. Villa A2

Luxury Villas In Lebanon - Progress Report August2020- img1
Luxury Villas In Lebanon - Progress Report August2020- img2
Figure 1 Ground floor slab formwork
Luxury Villas In Lebanon - Progress Report August2020- img3
Figure 2 Ground floor slab reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img4
Figure 3 Ground floor after casting of concrete
Luxury Villas In Lebanon - Progress Report August2020- img5
Figure 4 Formwork for ground floor columns
Luxury Villas In Lebanon - Progress Report August2020- img6
Figure 5 Ground floor columns after concrete casting along with some shutter work for the 1st floor slab
Luxury Villas In Lebanon - Progress Report August2020- img7
Figure 6 1st floor slab reinforcements, post-tension cables and electric cables
Luxury Villas In Lebanon - Progress Report August2020- img8
Figure 7 1st floor slab concrete cast and column reinforcements are prepared
Luxury Villas In Lebanon - Progress Report August2020- img9
Figure 8 1st floor columns cast
Luxury Villas In Lebanon - Progress Report August2020- img10
Figure 9 2nd floor slab formwork
Luxury Villas In Lebanon - Progress Report August2020- img11
Figure 10 During the concrete casting of slab
Luxury Villas In Lebanon - Progress Report August2020- img12
Figure 11 Stairs Reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img13
Figure 12 Applying SBS membrane insulation layer
Luxury Villas In Lebanon - Progress Report August2020- img14
Figure 13 Layers of isolation: Reparation coating, SBS membrane, Cartonal and Concrete Blocks
Luxury Villas In Lebanon - Progress Report August2020- img15
Figure 14 Quality control: Preparing concrete cylinders for compression testing
Luxury Villas In Lebanon - Progress Report August2020- img16
Figure 15 Swimming pool formwork
Luxury Villas In Lebanon - Progress Report August2020- img17
Figure 16 Swimming pool walls after concrete casting
Luxury Villas In Lebanon - Progress Report August2020- img18
Figure 17 Swimming pool after concrete casting
Luxury Villas In Lebanon - Progress Report August2020- img19
Figure 18 Attic roof form work and reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img20
Figure 19 Reinforcements details

2. Villa B1

Finished construction stages:
a) Basement columns and retaining walls
b) Ground floor slab
c) Basement block/partition walls

Luxury Villas In Lebanon - Progress Report August2020- img21
Luxury Villas In Lebanon - Progress Report August2020- img21
Figure 1 Basement Columns formwork and reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img22
Figure 2 Basement Columns after concrete cast
Luxury Villas In Lebanon - Progress Report August2020- img23
Figure 3 Ground floor slab formwork
Luxury Villas In Lebanon - Progress Report August2020- img24
Figure 4 Ground floor PT slab during concrete casting
Luxury Villas In Lebanon - Progress Report August2020- img25
Figure 5 Ground floor PT slab after concrete cast
Luxury Villas In Lebanon - Progress Report August2020- img26
Figure 6 Basement block wall
Luxury Villas In Lebanon - Progress Report August2020- img27
Figure 7 Walls insulation

3. Villa B2

Finished construction stages:
a) Excavation
b) Blinding concrete layer
c) Foundations
d) Column necks and retaining walls
e) Swimming Pool

Luxury Villas In Lebanon - Progress Report August2020- img28
Luxury Villas In Lebanon - Progress Report August2020- img29
Figure 1 Excavations
Luxury Villas In Lebanon - Progress Report August2020- img30
Figure 2 Foundations formworks and reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img31
Figure 3 Foundations after concrete cast
Luxury Villas In Lebanon - Progress Report August2020- img32
Figure 4 Swimming pool bottom reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img33
Figure 5 Swimming pool after concrete cast
Luxury Villas In Lebanon - Progress Report August2020- img34
Figure 6 Swimming pool walls after concrete cast

4. Villa B3

Finished construction stages:
a) Foundations
b) Basement slab on grade
c) Basement Columns and retaining walls
d) Swimming Pool

Luxury Villas In Lebanon - Progress Report August2020- img35
Luxury Villas In Lebanon - Progress Report August2020- img36
Figure 1 Foundations reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img37
Figure 2 Preparing Slab on grade reinforcements above a nylon layer
Luxury Villas In Lebanon - Progress Report August2020- img38
Figure 3 Foundations and slab on grade after concrete cast along with the column’s reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img39
Figure 4 Columns after concrete cast and formwork preparations for the ground floor slab
Luxury Villas In Lebanon - Progress Report August2020- img40
Figure 5 Part of the ground floor slab
Luxury Villas In Lebanon - Progress Report August2020- img41
Figure 6 Swimming pool

5. Villa B4

Finished construction stages:
a) Foundations
b) Basement Slab on grade
c) Basement Columns

Luxury Villas In Lebanon - Progress Report August2020- img42
Luxury Villas In Lebanon - Progress Report August2020- img43
Figure 1 Foundations reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img44
Figure 2 Foundations after concrete cast and Bitumen isolation
Luxury Villas In Lebanon - Progress Report August2020- img45
Figure 3 Slab on grade along with the MEP works
Luxury Villas In Lebanon - Progress Report August2020- img46
Figure 4 Ground floor columns

6. Villa B5

Finished construction stages:
a) Excavation
b) Blinding layer
c) Foundations
d) Column necks

Luxury Villas In Lebanon - Progress Report August2020- img47
Luxury Villas In Lebanon - Progress Report August2020- img48
Figure 1 Excavation and blinding layer
Luxury Villas In Lebanon - Progress Report August2020- img49
Figure 2 Foundations formwork and reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img50
Figure 3 Foundations after concrete cast and column necks reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img51
Figure 4 Concrete Column necks with Bitumen isolation

7. Villa B6

Finished construction stages:
a) Basement columns and retaining walls

Luxury Villas In Lebanon - Progress Report August2020- img52
Luxury Villas In Lebanon - Progress Report August2020- img53
Figure 1 Columns and retaining walls after concrete cast

8. Villa B7

Finished construction stages:
a) Basement columns and retaining walls

Luxury Villas In Lebanon - Progress Report August2020- img54
Luxury Villas In Lebanon - Progress Report August2020- img55
Figure 1 Basement columns and retaining walls after concrete cast

9. Villa C1

Finished construction stages:
a) Basement columns and retaining walls
b) Ground floor slab

Luxury Villas In Lebanon - Progress Report August2020- img56
Luxury Villas In Lebanon - Progress Report August2020- img57
Figure 1 Basement columns and retaining walls
Luxury Villas In Lebanon - Progress Report August2020- img58
Figure 1 High-quality plywood used for formwork
Luxury Villas In Lebanon - Progress Report August2020- img59
Figure 2 Retaining wall smooth surface after concrete cast
Luxury Villas In Lebanon - Progress Report August2020- img60
Figure 3 Ground floor slab post-tension strands
Luxury Villas In Lebanon - Progress Report August2020- img61
Figure 4 Additional reinforcements at the strand›s start
Luxury Villas In Lebanon - Progress Report August2020- img62
Figure 5 Ground floor slab during concrete casting

10. Villa C2

Finished construction stages:
a) Slab on grade
b) Basement columns and retaining walls
c) Ground floor slab

Luxury Villas In Lebanon - Progress Report August2020- img63
Luxury Villas In Lebanon - Progress Report August2020- img64
Figure 1 Slab on grade reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img65
Figure 2 Basement Column reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img66
Figure 3 Retaining walls constructed and first-floor slab formwork done
Luxury Villas In Lebanon - Progress Report August2020- img67
Figure 4 Concrete casting of the first-floor post-tension slab

11. Villa C3

Finished construction stages:
a) Ground floor slab on grade
b) Ground floor columns

Luxury Villas In Lebanon - Progress Report August2020- img68
Luxury Villas In Lebanon - Progress Report August2020- img69
Figure 1 Tie beams constructed between columns
Luxury Villas In Lebanon - Progress Report August2020- img70
Figure 2 Column necks reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img71
Figure 3 Insulating columns with Bitumen
Luxury Villas In Lebanon - Progress Report August2020- img72
Figure 4 Introducing fill material to reach the ground floor level
Luxury Villas In Lebanon - Progress Report August2020- img73
Figure 5 Ground floor slab on grade and columns

12. Villa C4

Finished construction stages:
a) Column necks
b) Ground floor slab on grade
c) Ground floor columns

Luxury Villas In Lebanon - Progress Report August2020- img74
Luxury Villas In Lebanon - Progress Report August2020- img75
Figure 1 Column necks after isolation and introduction of soil fill
Luxury Villas In Lebanon - Progress Report August2020- img76
Figure 2 Ground floor slab on grade
Luxury Villas In Lebanon - Progress Report August2020- img77
Figure 3 Ground floor columns

13. Villa C6

Finished construction stages:
a) Basement slab on grade
b) Basement columns and retaining walls
c) Ground floor

Luxury Villas In Lebanon - Progress Report August2020- img78
Luxury Villas In Lebanon - Progress Report August2020- img79
Figure 1 Slab on grade reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img80
Figure 2 Basement slab on grade
Luxury Villas In Lebanon - Progress Report August2020- img81
Figure 3 Tie beams and retaining walls formwork
Luxury Villas In Lebanon - Progress Report August2020- img82
Figure 4 Retaining walls after concrete cast
Luxury Villas In Lebanon - Progress Report August2020- img83
Figure 5 Ground floor slab reinforcements

14. Villa C7

Finished construction stages:
a) Foundations at basement level
b) Basement slab on grade
c) Basement columns and retaining walls
d) Ground floor slab

Luxury Villas In Lebanon - Progress Report August2020- img84
Luxury Villas In Lebanon - Progress Report August2020- img85
Figure 1 Foundations Reinforcements at basement level
Luxury Villas In Lebanon - Progress Report August2020- img86
Figure 2 Basement slab on grade
Luxury Villas In Lebanon - Progress Report August2020- img87
Figure 3 Basement columns formwork
Luxury Villas In Lebanon - Progress Report August2020- img88
Figure 4 Basement columns after concrete cast
Luxury Villas In Lebanon - Progress Report August2020- img89
Figure 5 Ground floor post-tension slab

15. Villa C8

Finished construction stages:
a) Excavations
b) Foundations reinforcements

Luxury Villas In Lebanon - Progress Report August2020- img90
Luxury Villas In Lebanon - Progress Report August2020- img91
Figure 1 Foundations Reinforcements

16. Villa C14

Finished construction stages:
a) Excavation
b) Blinding layer
c) Foundations
d) Columns necks and retaining walls
e) Basement slab on grade
f) Basement columns and retaining walls

Luxury Villas In Lebanon - Progress Report August2020- img92
Luxury Villas In Lebanon - Progress Report August2020- img93
Figure 1 Foundations Reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img94
Figure 2 Foundations after concrete cast and Bitumen isolation
Luxury Villas In Lebanon - Progress Report August2020- img95
Figure 3 Slab on grade reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img96
Figure 4 Basement slab on grade
Luxury Villas In Lebanon - Progress Report August2020- img97
Figure 5 Basement columns reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img98
Figure 6 Basement columns and retaining wall after concrete casting

17. Villa C15

Finished construction stages:
a) Excavation
b) Blinding layer
c) Foundations
d) Column necks and retaining walls
e) Basement slab on grade

Luxury Villas In Lebanon - Progress Report August2020- img99
Luxury Villas In Lebanon - Progress Report August2020- img100
Figure 1 Blinding layer and excavation
Luxury Villas In Lebanon - Progress Report August2020- img101
Figure 2 Foundations reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img102
Figure 3 Soil fill at the basement level
Luxury Villas In Lebanon - Progress Report August2020- img103
Figure 4 Basement columns and retaining walls

18. Villa D10

Finished construction stages:
a) Blinding layer
b) Foundations
c) Basement slab on grade
d) Basement columns and retaining walls
e) Ground floor slab shutter work

Luxury Villas In Lebanon - Progress Report August2020- img104
Luxury Villas In Lebanon - Progress Report August2020- img105
Figure 1 Blinding layer
Luxury Villas In Lebanon - Progress Report August2020- img106
Figure 2 Foundations reinforcements and formwork
Luxury Villas In Lebanon - Progress Report August2020- img107
Figure 3 Concrete foundations cast and soil fill introduced
Luxury Villas In Lebanon - Progress Report August2020- img108
Figure 4 Slab on grade reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img109
Figure 5 Ground floor PT slab reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img110
Figure 6 Basement roof after concrete cast

19. Villa D11

Finished construction stages:
a) Excavations

Luxury Villas In Lebanon - Progress Report August2020- img111
Luxury Villas In Lebanon - Progress Report August2020- img112
Figure 1 Excavations and foundations reinforcements

20. Villa D18

Finished construction stages:
a) Excavation
b) Blinding layer
c) Foundations
d) Column necks

Luxury Villas In Lebanon - Progress Report August2020- img114
Luxury Villas In Lebanon - Progress Report August2020- img115
Figure 1 Excavations
Luxury Villas In Lebanon - Progress Report August2020- img116
Figure 2 Concrete Foundations
Luxury Villas In Lebanon - Progress Report August2020- img117
Figure 3 Column necks reinforcements
Luxury Villas In Lebanon - Progress Report August2020- img118
Figure 4 Columns necks after isolating them and introducing soil fill

21. Villa E1

Finished construction stages:
a) Excavation
b) Blinding layer
c) Foundations

Luxury Villas In Lebanon - Progress Report August2020- img119
Luxury Villas In Lebanon - Progress Report August2020- img120
Figure 1 Excavations
Luxury Villas In Lebanon - Progress Report August2020- img121
Figure 2 Foundations
Luxury Villas In Lebanon - Progress Report August2020- img122
Figure 3 Column and retaining wall necks
Luxury Villas In Lebanon - Progress Report August2020- img123
Figure 4 Tie beam reinforcements at slab on grade level

22. Villa E2

Finished construction stages:
a) Excavation
b) Blinding layer
c) Foundations
d) Column and retaining wall necks

Luxury Villas In Lebanon - Progress Report August2020- img124
Luxury Villas In Lebanon - Progress Report August2020- img125
Figure 1 Excavation and blinding layer
Luxury Villas In Lebanon - Progress Report August2020- img126
Figure 2 Foundations, column necks and retaining walls

II. Walls

1. Villa B5 Walls

Luxury Villas In Lebanon - Progress Report August2020- img127
Luxury Villas In Lebanon - Progress Report August2020- img128

2. Villa C3 Walls

Luxury Villas In Lebanon - Progress Report August2020- img129
Luxury Villas In Lebanon - Progress Report August2020- img130

3. Villa C4 Walls

Luxury Villas In Lebanon - Progress Report August2020- img131
Luxury Villas In Lebanon - Progress Report August2020- img132

4. Villa C1-C5 Side Wall

Luxury Villas In Lebanon - Progress Report August2020- img133
Luxury Villas In Lebanon - Progress Report August2020- img134

5. Zone E Walls

Luxury Villas In Lebanon - Progress Report August2020- img135
Luxury Villas In Lebanon - Progress Report August2020- img136

III. Roads and Infrastructure

  • All main roads subgrade layers are finished and ready for asphalt pavement.
Luxury Villas In Lebanon - Progress Report August2020- img136
Luxury Villas In Lebanon - Progress Report August2020- img137
Luxury Villas In Lebanon - Progress Report August2020- img138
Luxury Villas In Lebanon - Progress Report August2020- img139
Luxury Villas In Lebanon - Progress Report August2020- img140
Luxury Villas In Lebanon - Progress Report August2020- img141

THANK YOU
WE WILL KEEP YOU UPDATED

Search articles

Book your demo now!

Recent posts